How long does a cold room installation take?
A small modular room is usually a few days on site once the base, power and drainage are ready.
Panel assembly is quick. The time goes into the base and floor, the electrical supply, the drain route, the plant position and commissioning. If those are ready, a small room can be assembled and running in a few days.
Working in an operating kitchen adds constraints: access, noise and the need to keep service running. That sequencing is agreed before the first day.
We confirm what must be in place beforehand so nobody is waiting on a missing connection.
This falls under cold room installation & repairs, which we cover in Muizenberg, Retreat, Heathfield and Southfield.